By providing your contact information to The Hayes Team, your personal information will be processed in accordance with The Hayes Team's Privacy Policy. By checking the box(es) below, you consent to receive communications regarding your real estate inquiries and related marketing and promotional updates in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. You may opt out of receiving further communications from The Hayes Team at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe.
Thank you for your message. We will be in touch with you shortly.
Explore Our Properties
A quiet meadow bordered by pines and autumn oaks, with a short dark pasture fence at the edge of the grass.

Where Every Data Center Proposal Around Newnan Stands Before the Dec. 1 Hearing

November 19, 2026

On Oct. 20, 2026, the Coweta County Board of Commissioners voted 3-2 to rezone 323.9 acres near Palmetto back to rural conservation. The land had been zoned light industrial for Project Peach since April 2025. The Newnan Times-Herald reported that the vote came after the project missed deadlines set in that 2025 approval, and that a CyrusOne representative had asked for more time. Commissioners Al Smith, Bob Blackburn and Bill McKenzie voted to revert the zoning, and Jeff Fisher and John Reidelbach voted against.

Peach shows how these projects have actually gone in Coweta. Of the three data center proposals commissioners have voted on so far, Sail kept its zoning and is being challenged in court, Oak was denied, and Peach was approved and later lost its zoning. The two projects that have published revised plans, Sail and Pegasus, both got smaller between the first filing and the latest version.

The First Number You Heard Was the Largest One

Project Sail is the biggest proposal and the one most people have heard of. When its Development of Regional Impact review was filed, it was described as 13 data halls totaling about 4.9 million square feet. The plan the county approved on April 7, 2026 caps the campus at nine buildings and 4.34 million square feet. The water estimate dropped further. In May 2025, WABE reported a maximum of 9 million gallons a day for Project Sail. The applicant's March 26, 2026 fact sheet puts full buildout at 300,000 gallons a day. About 100,000 of those gallons would evaporate, and about 200,000 would go to the Coweta County Water and Sewerage Authority's sewer system.

Project Pegasus has shrunk the same way. Its DRI listed 2.95 million square feet and 77,000 gallons of water a day. On Nov. 11, 2026, the Times-Herald reported that the developers now plan six data center buildings totaling 2.41 million square feet, using 54,000 gallons a day. The site itself got bigger, from the 200 acres listed earlier to 232 acres.

These plans keep changing, and they have changed because of the public process. If you read a figure from a year-old article about a site near a home you're considering, check it against the newest filing.

Five Sites, Four Directions From Downtown

Where each project sits matters as much as how big it is. Here is each site by direction from Newnan, with its status as of this week.

West, toward Sargent. Project Sail covers 829.41 acres at Welcome to Sargent Road and Wagers Mill Road, about seven miles northwest of Newnan, next to Georgia Power's Plant Yates. It was rezoned 3-2 on April 7, 2026. Reidelbach, Fisher and Smith voted yes, and McKenzie and Blackburn voted no. At that hearing, residents presented 7,820 signatures opposing the rezoning, according to the Times-Herald.

North, near Bullsboro Drive and I-85. Project Oak was planned for a 255-acre industrial parcel off Walt Sanders Road. Commissioners denied its rezoning unanimously on Aug. 25, 2026, the Times-Herald reported. The plan had called for access from extensions of Coweta Industrial Parkway and Hollz Parkway, both part of the Madras Connector project.

Northeast, toward Palmetto. Two proposals are close to each other here. Peach's land, now zoned rural conservation again, is off Highway 29, Weldon Road and Johnston Circle, a few miles from the Palmetto city limits. After the vote, Palmetto Councilmember Carolyn Wynn told the Times-Herald that the reversion "will save the city" from what she saw as negative impacts. Pegasus covers 232 acres along Palmetto-Tyrone Road and Weldon Road. It is still zoned rural conservation, and its rezoning hearing is set for Dec. 1, according to county communications manager Cathy Wickey. After an Oct. 22 community meeting, residents raised concerns about noise and light. A developer representative said the project would follow the county noise ordinance and use dark-sky lighting.

South, at Exit 41. The Bridgeport proposal would extend the existing Bridgeport Industrial Park with six data center buildings and on-site substations. The park already has industrial zoning, and the county has called for a fresh DRI review, the first since 2015. The park's main entrance is Bridgeport Parkway at U.S. 29, near I-85 Exit 41 in Moreland. The expansion area borders Bethlehem Church Road and Victoria Drive, though those roads are not regular industrial park entrances.

What Would Change First Near Sail

The first physical change on the ground would be road work. Sail's approved plan includes roundabouts at Wagers Mill Road and SR 16 and at Henry Bryant Road and SR 16, plus turn lanes on Welcome to Sargent Road and Wagers Mill Road. If you're looking at homes off SR 16 west of Newnan, those are the intersections to watch.

On May 5, 2026, residents asked Coweta County Superior Court to void the rezoning, The Citizen reported. A public case tracker counts 17 petitioners and listed the appeal as active when it was last reviewed on Nov. 5, 2026. At the April hearing, Prologis representative J.C. Witt told commissioners that construction could begin 12 to 18 months after the land purchase. He said the purchase could close by the end of this year. That is the developer's forecast, so the earliest construction start it describes is about a year away, and it depends on both the court case and the land closing.

The Tax Figures Are Projections

Each proposal has come with a revenue figure. Ahead of the April hearing, the Times-Herald reported that Sail's supporters cited about $100 million in tax revenue at full buildout. When Pegasus filed its DRI, it projected $3 million a year. That estimate came before the revised plan, so it may no longer match the project. Peach's development agreement required the developers to pay the county $2.5 million a year until the data center was operating or its net real property taxes passed that amount. Since Oct. 20, the Peach land has been zoned rural conservation.

The FY2027 draft budget presented in July 2026 totaled just over $177 million across the general and major service funds, with a proposed maintenance and operations rate of 4.090 mills. Staff said most property owners would see a net reduction, and they attributed that to new sales-tax proceeds and state rollback rules. This is general information, not tax or financial advice. Please check your own property tax situation with a qualified professional.

The 500-kV Line Is a Separate Project

Georgia Power's Ashley Park–Wansley project is a new 35-mile, 500-kV line from the Ashley Park Substation in Fayette County to Plant Wansley in Heard County, crossing Fulton and Coweta counties. According to the route notice published in Fayette County, the line would run southwest alongside the existing Morrow–Yates 115-kV corridor. It would cross I-85, U.S. 29/SR 14/SR 154 and SR 70 at Roscoe Road on the way to the Plant Yates area, with new easements 135 to 150 feet wide where needed. Georgia Power's project page says the line is not being built for any one customer and that its schedule is tentative. For a home near that corridor, Georgia Power's route updates are the record to follow.

The Dates to Watch This Winter

Commissioners adopted a data center ordinance on Dec. 16, 2025, and in June 2026 they placed a 180-day moratorium on data center development while they work on revisions. Staff brought revisions to a work session in October.

If you are comparing homes around Newnan over the next few months, these are the dates to know:

  1. Dec. 1: The Pegasus rezoning hearing for Palmetto-Tyrone Road and Weldon Road.
  2. Dec. 13: The date the moratorium is set to expire.
  3. No set date: A Superior Court ruling on the Sail appeal and the closing of the Sail land purchase.

If you're deciding between homes on different sides of Newnan, The Hayes Team can show you which of these sites is closest to each one and what has happened with it since it was first announced. Schedule your free consultation and home valuation, and we'll go through it with you before you make an offer.